DPIIT Project Financial Outlay

The Project cost and financial contribution by DPIIT, Govt of TamilNaduand DINTEC CETP

S.No Name of the Item / Component Amount Sanctioned (Rs. in Lakhs) As on 30.06.2021 Timeline
Expenditure incurred % of work completed committed Revised, if any
1. Raw Effluent Pumping Station 49.3 Nil Starting March 2020 July 2022
2. Collection & Screening System 177.16 5% Starting March 2020 July 2022
3. Improved Mixing in Equalization 27 Nil Starting March 2020 Commissioned on 25.10.2022
4. Aerobic Biological System 574 50% 50% March 2020 July 2022
5. New Final R.O 150 Nil Starting March 2020 July 2022
6. Mechanical Evaporator Improvements 215 20% Starting March 2020 July 2022
7. Instrumentation and Centralized SCADA & Monitoring and Control of Member units from CETP 213.7 Nil Starting March 2020 July 2022
8. Blending Arrangement 95 Nil Starting March 2020 Commissioned on 10.10.2020
9. Grid Based Solar Power Plant 800 40% 25% March 2020 Commissioned on 01.04.2022
10. Technical and Administrative charges (Maximum 4%) 92.04 25% 25% March 2020 July 2022
Total 2393 Lakhs