DPIIT Project Financial Outlay
The Project cost and financial contribution by DPIIT, Govt of TamilNaduand DINTEC CETP
S.No | Name of the Item / Component | Amount Sanctioned (Rs. in Lakhs) | As on 30.06.2021 | Timeline | ||
---|---|---|---|---|---|---|
Expenditure incurred | % of work completed | committed | Revised, if any | |||
1. | Raw Effluent Pumping Station | 49.3 | Nil | Starting | March 2020 | July 2022 |
2. | Collection & Screening System | 177.16 | 5% | Starting | March 2020 | July 2022 |
3. | Improved Mixing in Equalization | 27 | Nil | Starting | March 2020 | Commissioned on 25.10.2022 |
4. | Aerobic Biological System | 574 | 50% | 50% | March 2020 | July 2022 |
5. | New Final R.O | 150 | Nil | Starting | March 2020 | July 2022 |
6. | Mechanical Evaporator Improvements | 215 | 20% | Starting | March 2020 | July 2022 |
7. | Instrumentation and Centralized SCADA & Monitoring and Control of Member units from CETP | 213.7 | Nil | Starting | March 2020 | July 2022 |
8. | Blending Arrangement | 95 | Nil | Starting | March 2020 | Commissioned on 10.10.2020 |
9. | Grid Based Solar Power Plant | 800 | 40% | 25% | March 2020 | Commissioned on 01.04.2022 |
10. | Technical and Administrative charges (Maximum 4%) | 92.04 | 25% | 25% | March 2020 | July 2022 |
Total | 2393 | Lakhs |